| Client Name |
|
|
Bellin Hospital |
|
|
| |
|
|
Bellin Hospital is an acute care, 167-bed, multi-specialty hospital, employing approximately 2,300 people. |
|
 |
|
|
|
|
|
 |
|
|
|
|
|
| Building Type |
|
|
Healthcare |
|
|
 |
|
|
|
|
|
| Location(s) |
|
|
Green Bay, Wisconsin |
|
|
 |
|
|
|
|
|
| Date |
|
|
2004 |
|
|
 |
|
|
|
|
|
| Area Dimensions |
|
|
84,310 SF |
|
|
 |
|
|
|
|
|
| Facility Highlights |
|
|
| • |
Basement level: three 500 HP steam boilers, deaeration system, main campus electrical switchgear
|
| • |
First floor: loading docks, facilities offices, shipping/receiving office, cart-washing system, freight elevator access to basement level, provisions to hook-up a temporary portable emergency generator
|
| • |
Second floor: two 2,000 KW emergency generators, one 500 KW generator, three 700-ton chillers, plant maintenance offices/shops
|
| • |
Third floor: 3 independent cooling towers, contains cooling radiators for emergency generators, cooling towers mounted on roof surrounded by mansard roof screening
|
| • |
Tunnel: 20' wide, 800' long, passes beneath a city street, allows electric cart transport of goods/materials into the hospital |
|
|
|
 |
|
|
|
|
|
 |
2007 Somerville, Inc. |
|
|
|
|
|
|
 |
|